about us news initiatives contact join

 

 

News | Navigation Problems Report | Archive 2002 | Galveston

 
Mile Board

318.5 WHL 1st point east of High Island Bridge

Chart Number

11331

Problem

Shoaling.

Recommendation

Survey and dredge.

Status

October 1996, reported to Corps

CLOSED

Corps Project Manager

Joe Hrametz

Corps Action as of 9/11/02

This reach of the GIWW was last dredged in 1994 and is dredged every 8 to 10 years. A recent condition survey of the area was conducted on June 25, 2001, and does not indicate any critical shoaling near mile 318.5. Current depths in this area are as follows: south toe 13.0, centerline 15.5, and north toe 13.0.

 
Mile Board

Houston Ship Channel

Chart Number

11326

Problem

Widening and deepening project as currently designed will virtually eliminate the barge lanes between Redfish and Morgans Point.

Recommendation

Ensure that the 1,000-foot margin of safety is maintained all the way to Morgans Point.

Status

HR 2605 passed in 1999 directed the Corps to "plan and construct barge lanes immediately adjacent to either side of the Houston Ship Channel from Bolivar Roads to Morgans Point." Barge lanes have been included in the project and are under construction.

CLOSED

Corps Project Manager

Dalton Krueger

Corps Action as of 9/11/02

Barge lanes have been constructed in the lower one-third of Galveston Bay. The barge lanes in the upper two-thirds of Galveston Bay are currently under design and the Project Cooperation agreement for construction is being negotiated with the Port of Houston Authority. Fifty-four acres of oyster reef will be constructed to mitigate for the oysters destroyed during construction. Construction for both the barge lanes and the mitigation is scheduled to start in Janauary 2004 with completion of the barge lanes estimated to be October 2004.

 
Mile Board

Houston Ship Channel

Chart Number

11326

Problem

Atkinson Island moorings adrift and needing repair. Area needs dredging to be able to access buoys.

Recommendation

Remove buoys for use at other locations. Initiate 216 study to identify suitable locations in this vicinity protected from ship waves.

Status

Reported July, 2001.

CLOSED

Corps Project Manager

Bill Jakeway

Corps Action as of 9/11/02

Buoys will be removed in August 2002 using maintenance contract. Relocation study will be requested in FY 03.

 
Mile Board

363-364 WHL

Chart Number

11322

Problem

Washout on south bank and shoaling on north bank.

Recommendation

Reestablish the south bank to prevent shoaling in the waterway and eventual erosion of the north bank.

Status

Area is under Corps 216 for improvements from High Island to Brazos River. Extensive shoaling in this area reported July, 2001.

CLOSED

Corps Project Manager

Mike Bragg

Corps Action as of 9/11/02

This specific problem was not identified in the reconnaissance phase of the 216 study and is therefore not currently being addressed. However, this could be addressed in a Post Authorization action in the near future. The Corps will investigate the problem and meet with GICA to discuss possible course for action.

 
Mile Board

383 WHL

Chart Number

11322

Problem

Erosion control structures present hazards to navigation on north bank of Waterway.

Recommendation

Light and mark structures or redesign so as not to present hazard to barge traffic.

Status

Reported July, 2001.

Texas Parks and Wildlife is determined to be owner.

CLOSED

Corps Project Manager

Joe Hrametz

Corps Action as of 9/11/02

 

 
Mile Board

420 WHL

Chart Number

none

Problem

Shoaling is reported in the middle of the channel.

Recommendation

Dredge the area as quickly as possible.

Status

Reported to the Corps of Engineers January 14, 2002.

Project completed at of 7/16/02 update.

CLOSED

Corps Project Manager

Joe Hrametz

 
Mile Board

440 WHL Colorado Locks

Chart Number

11319

Problem

Existing mooring buoys need repair.

Recommendation

Repair buoys.

Status

Reported July, 2001.

CLOSED

Corps Project Manager

Bill Jakeway

Corps Action as of 9/11/02

Colorado River Locks - 42 buoys. Damaged buoys were replaced with new buoys in July 2002.

 
Mile Board

502 WHL

Chart Number

11315

Problem

Shoaling on both the north and south side, limiting traffic to one way passage.

Recommendation

Survey and dredge.

Status

February 1995, reported to the Corps.

CLOSED

Corps Project Manager

Joe Hrametz

Corps Action as of 9/11/02

This reach of the GIWW is currently under contract. Dredging will be completed by 1 Oct 01.

 
Mile Board

511-516 WHL

Chart Number

11315

Problem

Shoaling in entire area.

Recommendation

Dredge this section back to project dimensions.

Status

Reported July, 2001.

CLOSED

Corps Project Manager

Joe Hrametz

Corps Action as of 9/11/02

This reach of the GIWW was scheduled to be performed 3rd-QTR of FY-01; however, due to funding shortfall work had to be reprogrammed in 3rd-QTR of FY-02. This work falls within critical habitat; therefore work can only be performed between April and September.

 

webmaster@gicaonline.com | © Gulf Intracoastal Canal Association