|
|
| |
| Mile
Board |
319 to 323 WHL (High Island
Bends) |
| Chart
Number |
11331 |
| Problem |
Several consecutive bends
are difficult to transit, making this area extremely hazardous. |
| Recommendation |
Widening and easening bends,
proved to be successful in simulator study. |
| Status |
Simulator project
has been completed. The Section 216 study will continue in
order to address placement area capacity that remains an issue. |
| Corps
Project Manager |
George Alcala |
| Corps
Action as of 7/27/04 |
The Section 216 study reviewed
widening and/or realigning three bends at the High Island
location, based on waterway users input and vessel simulations
conducted at the Engineering Research Development Center.
These three segments of the waterway were omitted from the
feasibility report, which was completed in September 2003,
due to placement area capacity issues. However, these issues
will be addressed during subsequent studies that will be conducted
upon receipt of additional GI funds. |
|
| |
| Mile
Board |
329 WHL (Rollover Bay) |
| Chart
Number |
11331 |
| Problem |
Existing channel width
combined with current and wind conditions greatly limit doubled-up
tow movements. Meeting situations are especially difficult.
Groundings and buoy discrepancies result. |
| Recommendation |
Request widening of Rollover
Bay by about 50-80 feet to the south. |
| Status |
Reported May, 2002. |
| Corps
Project Manager |
Not assigned |
| Corps
Action as of 7/27/04 |
This specific
problem was not identified in the reconnaissance phase of
the 216 study and is therefore not currently being addressed.
Alternate funding will have to be pursued for this
project. The 216 study addresses the segment of the waterway
associated with the Rollover
Pass, where a sediment trap was proposed in the Feasibility
Report dated September 2003. However, FY 06 funds were dedicated
to developing “draft” P&S for the Texas City
Wye and Pelican Island Moorings segments of the GIWW system. |
|
| |
| Mile
Board |
343 WHL (Sievers Cove) |
| Chart
Number |
11331 |
| Problem |
Shoaling north bank at Sievers Cove. |
| Recommendation |
Consider reestablishing north bank to
reduce shoaling and strong currents in the GIWW. |
| Status |
Area reviewed under Corps 216 study for improvements from High Island to Brazos River in the Feasibility Study that was completed in September 2003.
Problem still exists. |
| Corps
Project Manager |
George Alcala |
| Corps
Action as of 7/27/04 |
Under the 216
study, it was determined based on waterway user input and
past dredging
records, that current and wind from East Bay cause the most
problems to traffic. Therefore, the Corps determined that
widening the GIWW channel along the west approach to the gap
is the selected alternative, and would give pilots additional
maneuvering room to position their tows northward when crossing
the gap during prevailing northerly winds. The bottom of the
channel will be widened 75' on its north side of the GIWW.
The pilots were queried about the length of the channel to
be widened; their response was to open up the entire length
of channel constriction westward until the channel became
sufficiently wide enough, approximately 1400 feet, including
transitions. This segment of the GIWW received limited PED
funding in FY 05. FY 06 funds were dedicated to developing
“draft” P&S for the Texas City Wye and Pelican
Island Moorings segments of the GIWW system. |
|
| |
| Mile
Board |
348 to 349 WHL (Port Bolivar) |
| Chart
Number |
none |
| Problem |
Tight channel entrance
forces tows to "crab" as they transit in order to
counteract current and wind conditions. Repeated knockdowns
and buoy hull discrepancies show traffic is repeatedly set
along the green (southern) side of the channel. |
| Recommendation |
Request widening
of the southern side of Bolivar Peninsula (locally known as
the Bolivar Buoys) from mile 349.4 to mile 348.6. |
| Status |
Reported May, 2003.
|
| Corps
Project Manager |
Not assigned |
| Corps
Action as of 7/27/04 |
This specific
problem was not identified in the reconnaissance phase of
the 216 study and is therefore not currently being addressed.
Alternate funding will have to be pursued for this
project. |
|
| |
| Mile
Board |
351-352 WHL (Pelican Island Moorings) |
| Chart
Number |
11322 |
| Problem |
Insufficient mooring buoys available.
Tows double up on buoys creating traffic hazard and damaging
buoys. |
| Recommendation |
Install at least 3 additional buoys to
the west of existing buoys. |
| Status |
Reported July 2001. |
| Corps
Project Manager |
George Alcala |
| Corps
Action as of 7/27/04 |
The Section
216 study (Feasibility Report completed September 2003) recommends
widening the existing basin to provide the needed channel
clearance. The bottom of the mooring basin will be widened
80 feet to the north, more than doubling its present width
of 75 feet, yielding a total width of 155 feet. In conjunction
with the widening, the 13 existing mooring buoys will be cut
away from their anchors and set back 80 feet. This design
has been coordinated with waterway users. This segment of
the GIWW received limited PED funding in FY 05. FY 06 funds
were dedicated to developing “draft” P&S for
the Texas City Wye and Pelican Island Moorings segments of
the GIWW system. |
|
| |
| Mile
Board |
364-365 WHL (Greens Lake Mooring Facility) |
| Chart
Number |
11322 |
| Problem |
Need mooring buoys at this location to
provide safe "waiting weather" spot for Galveston
Bay crossing. |
| Recommendation |
Install 6 mooring buoys on south bank
near Greens Cut. Insure placement out of main navigation channel. |
| Status |
Reported July, 2001. |
| Corps
Project Manager |
George Alcala |
| Corps
Action as of 7/27/04 |
The Section
216 study (Feasibility Report completed September 2003) recommends
that a new mooring basin with 7 mooring buoys be constructed
at the mouth of Greens Lake. The location and design was selected
through coordination with waterway users. This segment of
the GIWW has received limited PED funding in FY 05. FY 06
funds were dedicated to developing “draft” P&S
for the Texas City Wye and Pelican Island Moorings segments
of the GIWW system. |
|
| |
| Mile
Board |
370.5 - 371.7 WHL (northeast of Halls Lake) |
| Chart
Number |
11322 |
| Problem |
Very rapid erosion of the islands on the
south side of the GIWW is occurring in this area. |
| Recommendation |
Reestablish the south bank to prevent
shoaling in the waterway and eventual erosion of the north
bank. |
| Status |
April 2003, problem still exists. |
| Corps
Project Manager |
Vacant |
| Corps
Action as of 7/27/04 |
This specific
problem was not identified in the reconnaissance phase of
the 216 study and is therefore not currently being addressed.
Alternate funding will have to be pursued for this
project. |
|
| |
| Mile
Board |
372 - 374 WHL (West Bay Washout) |
| Chart
Number |
11322 |
| Problem |
West Bay breached this entire section
on the south bank of the GIWW. The Corps of Engineers replaced
one-third of the bank with dredge material that is eroding.
Some fabric tubes were used. |
| Recommendation |
Install 24-foot circumference by 10,058-foot-long geotubes between GIWW and the West Bay, offset 300 feet from the centerline of the channel. Additionally, install an estimated 39,500 SF cellular concrete mattress along the channel's north shoreline, which would separate the GIWW from Halls Lake. |
| Status |
April 2003, problem still exists. |
| Corps
Project Manager |
George Alcala |
| Corps
Action as of 7/27/04 |
The Section
216 study (Feasibility Report completed September 2003) recommends
a single geotube be constructed on the south bank of the GIWW
to provide protection to the channel. The study also recommended
using concrete mat on the northern bank to prevent further
erosion between Halls Lake and the GIWW. This segment of the
GIWW received limited PED funding in FY 05. FY 06 funds were
dedicated to developing “draft” P&S for the
Texas City Wye and Pelican Island Moorings segments of the
GIWW system. |
|
| |
| Mile
Board |
392 WHL-395 WHL (Freeport Wiggles) |
| Chart
Number |
11322 |
| Problem |
Several consecutive bends make a difficult
and dangerous bridge approach and cause one way traffic. |
| Recommendation |
Make straight channel alignment to bridge,
as proved to be successful in simulator study. Simulator project has been completed. The Section 216 study will continue in order to address real estate and environmental issues that remain unresolved. |
| Status |
The area is under the Corps 216 study
for improvements from High Island to Brazos River.
July 2001- problem still exists. |
| Corps
Project Manager |
George Alcala |
| Corps
Action as of 7/27/04 |
The Corps has
examined bend widening/easing as well as channel realignment
opportunities. According to waterway users and vessel simulations,
the bend widening/easing was not successful in addressing
existing traffic problems. The realignment alternative did
improve navigation through the reach but the Corps has not
been able to justify the high cost and adverse environmental
impacts that would result from the same. Therefore, this segment
of the GIWW was omitted from the feasibility report, which
was completed in September 2003. However, these issues will
be addressed during subsequent studies that will need to be
conducted upon receipt of additional GI funds. Safety concerns
will be stated in subsequent studies/reports. The study received
limited funds in FY 05. The project is not currently in the
FY 06 budget. |
|
| |
| Mile
Board |
400.5 WHL Brazos Floodgates |
| Chart
Number |
11322 |
| Problem |
The current has increased significantly
in the west gate over time. Approach to both gates is hazardous
in high water. |
| Recommendation |
Study completely removing both gates. |
| Status |
1993, reported to the Corps of Engineers.
April 2003, problem is getting worse. |
| Corps
Project Manager |
Mike Bragg |
| Corps
Action as of 7/30/06 |
Initiated Section
216 Study GIWW Modifications to examine possible modifications
to existing structure. Reconnaissance phase study has been
completed. The feasibility phase study is on hold pending
funding. The GIWW Modifications Study was suspended in FY
2004 to provide funds for other projects with critical milestones.
Insufficient funds were received in FY 2005 to accomplish
any milestones on the study and funds were reprogrammed to
another study .The GIWW Modifications Study was not funded
in FY 2006 and is not in the President's Budget for FY 2007.
The Possibility of removing gates will be addressed in feasibility
phase. Study effects of San Bernard River Gulf opening is
on hold and will be studied as part of the section 216 GIWW
Modifications study with the floodgates as one whole system. |
|
| |
| Mile Board |
(Brazos River intersection) |
| Chart Number |
none |
| Problem |
Of the ten buoys placed just east of the Brazos intersection, only 5 are functional (2 on the north bank and 3 on the south bank). |
| Recommendation |
Repair or replace non-fuctional buoys and double the number of buoys available. |
| Status |
Corps is currently addressing buoy repairs at Pelican Island and Bolivar. The Brazos intersection is next on the list. New "floating anvil" style buoys will be placed for evaluation in April or May. If the new design works well, additional buoys of the same type should be feasible without much deliberation. |
| Corps Project Manager |
|
| Corps Action as of 7/27/04 |
Reported to Bill Jakeway, Galveston Corps District, February 14, 2005. |
|
| |
| Mile
Board |
420 WHL "Caney Creek Wiggles" |
| Chart
Number |
none |
| Problem |
Bends in waterway create slow traffic,
waiting and unsafe passages. |
| Recommendation |
Recommend shaving of banks to straighten
bends. |
| Status |
Reported to the Corps of Engineers 2002.
Proposed bend easing solution to be handled
under Section 224 authority. Team is investigating safety
and clearance issues related to the Sargeant Beach project. |
| Corps
Project Manager |
Dennis Thomas |
| Corps
Action as of 7/27/06 |
The project has been temporarily suspended due to lack of funds. |
|
| |
| Mile
Board |
441 WHL Colorado Locks Bypass Channel |
| Chart
Number |
11319 |
| Problem |
In July 1992, the bypass channel was opened
between the east locks and the FM 2031 swing bridge. Tows
are experiencing cross-current-related tow control problems.
The Corps of Engineers has imposed tow size limits at higher
current rates, requiring tripping. This area is extremely
hazardous for both commercial and recreational vessels. |
| Recommendation |
Study removal of both locks and increasing
the depth of the bypass channel at the intersection with the
GIWW. Physical model study at WES proved no navigation improvements
could be made to the existing conditions. |
| Status |
Galveston District initiated Section 216
feasibility phase study for the Colorado River Locks in October
2001. The study will examine possible modifications to existing
structures including removal of both locks. Comprehensive
study is ongoing at Engineering Research and Development Center
(ERDC) to address the currents at the GIWW and mouth of bypass
channel. |
| Corps
Project Manager |
Mike Bragg |
| Corps
Action as of 7/30/06 |
The feasibility
study for the GIWW Modifications, Colorado River Locks was
suspended in FY 2004 to provide funds for other projects with
critical milestones. Analyses have not progressed to the point
where a recommendation can be made. Navigation simulation
study is complete. Analysis of current at GIWW and mouth of
bypass channel completed. A small channel south of the diversion
dam will be the recommended plan to reduce recreational traffic
through the locks. ERDC modeling did not show a significant
reduction of crosscurrents with Southwest Cut opened. Additional
modeling is required to quantify the impacts of opening the
southwest cut on sediment and dredging frequency at the jetties.
No funds were received in FY 2006 for the diversion channel
or jetty analysis, and no funds are in the President's FY
2007 budget. |
|
| |
| Mile
Board |
471 WHL (Matagorda Bay Re-route) |
| Chart
Number |
11319 |
| Problem |
Shoaling, because this is an area of significant
crosscurrent and requires more frequent dredging than in the
past. |
| Recommendation |
Relocate GIWW further north to take advantage
of the natural deep water and avoid these strong crosscurrents. |
| Status |
February, 2001, Matagorda Ship Channel
area dredged to provide for 12 foot drafts. Overall alternate
route limited to 10 foot drafts. Survey of pipelines from
MSC to Port O'Connor to be done 4th Qtr. 2001 and every 6
months thereafter until project is complete. |
| Corps
Project Manager |
Dennis Thomas |
| Corps
Action as of 7/27/06 |
Feasibility
report was completed in June 2002. Project authorization pending.
Pre-construction, Engineering and Design (PED) phase was initiated
and had to stop due to funding shortfall in FY 04. Survey
of the beneficial use sites is needed; however, core borings
efforts are complete. Restart PED when funding is received. |
|
| |
| Mile
Board |
475 WHL (west of Port O’Conner
to Corpus) |
| Chart
Number |
11319 |
| Problem |
Mooring buoys present obstructions to
traffic in waterway due to their location in a congested area. |
| Recommendation |
Relocate buoys west of Port O'Connor and
locate out of main channel of waterway. |
| Status |
Entered on problem report July, 2001.
Project team has identified potential new location for mooring buoys, however, property ownership and right has become an issue. Real estate was working to resolve the issue. |
| Corps
Project Manager |
Dennis Thomas |
| Corps
Action as of 7/27/06 |
Plans to reprogram
funds to existing study for restart. |
|
| |
| Mile
Board |
492 WHL (Channel to Victoria) |
| Chart
Number |
11315 |
| Problem |
Navigation aids cannot be kept in place
in "Y" of intersection with Victoria Barge Canal
due to narrow channel width in the turn. |
| Recommendation |
Increase width of channel throughout intersection
turns. |
| Status |
Reported July, 2001. |
| Corps
Project Manager |
Ricky Villagomez |
| Corps
Action as of 8/08/06 |
At this time,
the total removal of the split appears to be the best alternative.
A ship simulation is required. The feasibility study continues
to address this and other problem areas, however, the project
has been temporarily suspended due to lack of funds. |
|
| |
|
webmaster@gicaonline.com | © Gulf Intracoastal Canal Association |
|